Part One – The Management Agreement
When Augusta’s Trade, Exhibition and Event (TEE) center was
approved in 2007, prudence might have suggested that one of the first steps in
the process of building the facility might have been to execute the Management
Agreement in advance. This being
Augusta, Georgia, where almost nothing is done in accordance with normal
business practices, the building has gotten within weeks of being used before a
management agreement was even submitted to Augusta commissioners for approval.
Worse, the management agreement was one of a covey of documents to flush out
for approval.
A very rapid assessment of the provisions of the contracts
was needed, because the proposed Manager immediately began hawking the loss of
events that might result if the Augusta Commission has the temerity to actually
deliberate on the terms and conditions of the entire contract documents.
The following represents a summary of the primary Management
Agreement issues compiled from a review of the contract documents. This list
has been provided to Commissioners and has become the basis of discussion and
attempts toward a speedy resolution of major issues. The approach was to review
the agreements in PDF form, write
comments, apply sticky notes that Adobe Acrobat provides to annotate documents,
and then to provide a summary from the compiled sticky notes.
Solutions were designed to be the product of meeting
participants and were not suggested in the summary.
The author is not a licensed attorney, auditor, or public
accountant. This analysis was provided from a multidisciplinary perspective in the
manner that accountants, attorneys, administrators, owners, policy makers, and
media might find useful in trying to decipher the pitfalls and dangers in the
agreements.
Tee Management
Agreement Major Issues at 11/2/2012
1. Differences in 2007 and 2009 Commission
Approvals and these Documents. No cost cap. Unlimited conduit to Augusta
General Fund.
2. Cost shifting between agreements. Electric utility
example. Beer inventory example. $300,000 a year for 50 years = $15,000,000
( Augusta’s Laney Walker Improvement cost calculation method)
3. Kitchen built under Tee Agreement where
ARLLC supplies equipment switches to 50 year Conference Agreement where Augusta
supplies and repairs kitchen equipment with no revenue from Conference Center.
4. No accounting provisions for backcharged
labor to Hotels or any other credits, refunds, rebates, or other benefits going
to Augusta.
5. Cross indemnification between Tee and
Conference Center – sever-ability issues. WHO IS LIABLE?
6. Too many ways to circumvent Annual Plan,
including that an unknown, unknowable “Standard” trumps everything, including
Annual Plan.
7. Fringe benefits and bonuses, including for
LLC PRINCIPALS, are unlimited.
8. Accounting and auditing envision most of
the accounting off TEE Center books, without rights of audit to ALL HOTEL
ACCOUNTING records on a real time basis.
9. Conventions can be booked using Tee
Exhibition Hall while using Conference Center where Augusta gets no revenues.
10. When Augusta signs these contracts, it
assumes extraordinary indemnity provisions immediately so that it would have to
advance payments to the Manager to defend the Manager from actions by Augusta
Time will tell how many of the above issues are addressed,
handled, and rectified.
-AG